Audience: customers with a Novatech Proxmox support agreement
Applies to: all tickets
The four priorities
Every ticket carries one of four priorities. The engineer sets it at triage from the business impact you describe, so describe the impact clearly when you raise the ticket.
| Priority | Portal label | What it means |
|---|---|---|
| P1 Critical | Urgent | Complete service outage, risk of data loss, or a production cluster is down. |
| P2 High | High | Significant impact on operations but a workaround exists, or a single node has failed in a cluster that is still serving. |
| P3 Medium | Medium | Limited impact, non-production systems affected, or degraded performance. |
| P4 Low | Low | General questions, minor issues, change requests, advisory questions. |
Response targets for each priority, in Business Hours and out of hours, are in PSS-SLA-001 "Proxmox Support Services Service Level Agreement", clauses 4 and 5. This article does not repeat them.
Who decides
The Novatech engineer assigns the priority on initial assessment, using the definitions above. If your view of the impact differs, say so in the ticket and the engineer will review it with you.
Asking for a change
- To raise a priority: add a note to the ticket explaining what has changed, for example a workaround has stopped working or more users are affected. Out of hours, customers with the 24/7 product telephone the support number, 02392 322555, for P1 and P2 impact. Portal and email notes are not read out of hours.
- To lower a priority: once a workaround is in place and the business impact is reduced, the engineer may propose a downgrade for root-cause work. This happens with your agreement, never silently. See PSS-SLA-001, clause 7.
Resolution and reopening
A ticket is resolved when normal service is restored and you confirm it, or after a set period without further contact from you. We tell you before we close a ticket on elapsed time. If the same issue returns within a short period we reopen the original ticket rather than start a new one. The periods are in PSS-SLA-001, clause 7.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article